Kings Quarter Regeneration

Meeting: 10/07/2019 - Cabinet (Item 24)

24 Kings Quarter Regeneration pdf icon PDF 140 KB

To consider the report of the Cabinet Member for Regeneration and Economy seeking to secure approval for the lease surrender of Bruton Way car park, extension of the project management contract and the necessary capital enabling costs to carry forward the momentum generated by the Kings Quarter regeneration project and ready the site for development.

 

 

Please note that Appendix A is exempt from disclosure to the press and public by virtue of Paragraph 3 (information relating to the financial or business affairs of any particular person, including the authority that holds the information) of Schedule 12A of the Local Government Act 1972 as amended. If Members wish to discuss Appendix A the Cabinet will need to resolve to exclude the press and public before doing so.

Additional documents:

Decision:

RESOLVED that:

 

(1) the following activities be approved to assist in achieving the accelerated delivery programme for enabling the development of Kings Quarter and ensuring that the pace of change can be continued if planning permission is granted:

 

a) the surrender back to the Council of the present long lease to NCP Limited for the Bruton Way multi-storey car park at the earliest opportunity, upon terms approved by the Property Commissioning Manager in consultation with the Head of Policy and Resources.

 

b) the extension of the contract for the Kings Quarter dedicated project management resource from 7thJuly 2019 until 6th January 2020, as envisaged by the original Cabinet approval dated 22nd June 2016, with Reef Estates Limited and to authorise the waiver of the contract rules under rule 6.1.5.

 

c) the allocation of additional costs required in respect of the determination of the Planning application for Kings Quarter and Kings Square as set out in Appendix A Table 1 of the report.

 

d) the demolition of Bruton Way Car Park, Bentinck House and partial demolition of the northern end of Grosvenor House.

 

(2) it be noted that subject to any necessary consents being obtained and the bids from the procurements listed in recommendation (1) and Appendix A, Table 1 in the report being in budget the Council will award the contracts (having first followed the appropriate decision making process) to enable those works to be undertaken after determination of the planning application.

 

(3) it be noted that further budget will need to be identified for the next phases of the regeneration programme. Future Enabling Works associated with this have been listed in Appendix A Table 2 of the report.

Minutes:

Cabinet considered the report of the Cabinet Member for Regeneration and Economy that sought to secure approval for the lease surrender of Bruton Way car park, extension of the project management contract and the necessary capital enabling costs to carry forward the momentum generated by the Kings Quarter regeneration project and ready the site for development.

 

The Cabinet Member for Regeneration and Economy summarised the report and stressed the importance of continuing the momentum of regeneration for Kings Quarter.  He further advised members on the benefits of the proposals to remove buildings in visibly poor condition and conduct archaeological investigations which will inform future development. 

 

RESOLVED that:

 

(1) the following activities be approved to assist in achieving the accelerated delivery programme for enabling the development of Kings Quarter and ensuring that the pace of change can be continued if planning permission is granted:

 

a) the surrender back to the Council of the present long lease to NCP Limited for the Bruton Way multi-storey car park at the earliest opportunity, upon terms approved by the Property Commissioning Manager in consultation with the Head of Policy and Resources.

 

b) the extension of the contract for the Kings Quarter dedicated project management resource from 7thJuly 2019 until 6th January 2020, as envisaged by the original Cabinet approval dated 22nd June 2016, with Reef Estates Limited and to authorise the waiver of the contract rules under rule 6.1.5.

 

c) the allocation of additional costs required in respect of the determination of the Planning application for Kings Quarter and Kings Square as set out in Appendix A Table 1 of the report.

 

d) the demolition of Bruton Way Car Park, Bentinck House and partial demolition of the northern end of Grosvenor House.

 

(2) it be noted that subject to any necessary consents being obtained and the bids from the procurements listed in recommendation (1) and Appendix A, Table 1 in the report being in budget the Council will award the contracts (having first followed the appropriate decision-making process) to enable those works to be undertaken after determination of the planning application.

 

(3) it be noted that further budget will need to be identified for the next phases of the regeneration programme. Future Enabling Works associated with this have been listed in Appendix A Table 2 of the report.