Agenda and minutes

Venue: Civic Suite, North Warehouse, The Docks, Gloucester, GL1 2EP. View directions

Contact: Democratic and Electoral Services 

Items
No. Item

33.

Declarations of Interest

To receive from Members, declarations of the existence of any disclosable pecuniary, or non-pecuniary, interests and the nature of those interests in relation to any agenda item. Please see Agenda Notes.

Minutes:

 No declarations were made on this occasion.

34.

Minutes pdf icon PDF 167 KB

To approve as a correct record the minutes of the meeting held on 4th September 2018.

Minutes:

The minutes of the meeting held 4th September 2018 were confirmed and signed by the Chair as a correct record.

35.

Late Material pdf icon PDF 139 KB

Please note that any late material relating to the applications listed below will be published on the Council’s website as a supplement in the late afternoon of the day of the meeting.

Minutes:

Late material in respect of Agenda items 5, 6 & 7 had been circulated.

 

 

 

 

 

 

36.

Land at Monkmeadow, Bakers Quay and Llanthony Wharf - 18/00685/FUL pdf icon PDF 727 KB

Application for determination:-

 

Variation of Condition 5 (to alter application plans and documents), 6 (to alter masterplan) and 73 (to reduce affordable housing provision) of permission ref. 14/00709/FUL as varied on land at Monkmeadow, Bakers Quay and Llanthony Wharf.

Minutes:

The Principal Planning Officer presented the report which detailed an application for variation of Condition 5 (to alter application plans and documents), 6 (to alter masterplan) and 73 (to reduce affordable housing provision) of permission ref. 14/00709/FUL (as varied) on land at Monksmeadow, Bakers Quay and Llanthony Wharf.

 

He advised that this application needed to be approved before the next application for reserved matters could be determined as the latter application was not compliant with the Master Plan which had been prepared some fifteen years previously.

 

He drew Members’ attention to the late material which contained which provided an update on the terms of the proposed Section 106 Agreement.

 

Sarah Hawkins for Peel and Emma Geater for Crest Nicholson addressed the Committee in support of the application.

 

A Member expressed concern at the low level of affordable housing and he asked if consideration had been given to using some of the funding for towpath enhancement to provide more affordable housing. He was advised that the towpath improvements were part of the open space offer from the development and were considered as such by the Inspector on the original application. Not securing the funds for the towpath would prevent the scheme from delivering the enhancement.

 

Another Member called for safety railings along the towpath which was used by many cyclists. He was advised that this was outside of the application site and not been considered necessary as a requirement of the outline planning permission.

 

The Chair moved and the Vice-Chair seconded that the Planning Technical Manager be authorised to grant planning permission subject to terms detailed in the late material.

 

RESOLVED that the Planning Technical Manager be authorised to grant planning permission subject to the satisfactory completion of a legal agreement to secure the following heads of terms, and the addition/variation of conditions as appropriate.

Towpath

-    Financial contribution of £320,000 (index linked)

-    To be paid towards enhancement of towpath in vicinity of application site

-    Payable upon commencement of development

 

Affordable Housing

-       1.2% (with no public subsidy) or up to 3.9% (with public subsidy) affordable housing (5 / 16 units) within the Monk Meadow phase (requiring a variation of Condition 73 and a legal agreement clause to set out the public subsidy testing process)

-       Mix of affordable housing provision being all affordable rent (this would be agreed via a further separate submission under Condition 73)

-       Delivery of affordable housing prior to 50% open market units (again this would be agreed via a further separate submission)

Monitoring fees

 

37.

Land at Monkmeadow - 18/00680/REM pdf icon PDF 435 KB

Application for determination:-

 

Reserved Matters approval for access, appearance, landscaping, layout and scale, for 409 residential units pursuant to outline permission 14/00709/FUL (as varied) for the Monk Meadow phase (phase G).

 

Minutes:

The Principal Planning Officer presented the report which detailed an application for Reserved Matters approval for access, appearance, landscaping, layout and scale for 409 residential developments pursuant to outline permission ref. 14/00709/FUL (as varied) for the Monk Meadow phase (phase G).

 

He drew Members’ attention to the late material which contained an update on amended plans, the views of the Highway Authority and a revised recommendation by the Planning Technical Manager.

 

The Vice-Chair expressed concern regarding the noise from generators on boats using the moorings and he asked if an electrical connection would be available to serve the pontoons. He was advised that the applicants had said that they would provide an electricity supply to the site boundary. The Canal and River Trust may then be able to provide an onwards connection.

 

A Member expressed concerns that the flats adjacent to the petrol filling station and car wash were to be above the garages and would be open to disturbance. He was advised that the issue had been picked up in the noise report submitted by the applicants; the design had been tested for a satisfactory living environment and the building type had been altered for these plots with the omission of rear windows facing the filling station.

 

The Chair moved and the Vice-Chair seconded that the Planning Technical Manager be authorised to grant reserved matters approval subject to the conditions contained in the late material.

 

RESOLVED that, providing application ref. 18/00685/FUL is granted planning permission, the Planning Technical Manager be authorised to grant reserved matters approval subject to the following conditions;

Condition 1

The development shall be carried out in accordance with the following plans;

 

Masterplan A-90-001 Rev. P received by the Local Planning Authority on 1st October 2018

 

Proposed floor plans Blocks 1 & 17 A-00-001 Rev. A received by the Local Planning Authority on 17th August 2017

Proposed elevations Blocks 1 & 17 A-01-001 Rev. A received by the Local Planning Authority on 17th August 2018

 

Proposed floor plans Block 2  A-00-002 Rev. A received by the Local Planning Authority on 17th August 2018

Proposed elevations Block 2 A-01-002 Rev. A received by the Local Planning Authority on 17th August 2018

 

Proposed floor plans Block 3 A-00-003 Rev. A received by the Local Planning Authority on 17th August 2018

Proposed elevations Block 3 A-01-003 Rev. A received by the Local Planning Authority on 17th August 2018

 

Proposed floor plans Block 4 A-00-004 Rev. A received by the Local Planning Authority on 17th August 2018

Proposed elevations Block 4 A-01-004 Rev. A received by the Local Planning Authority on 17th August 2018

 

Proposed floor plans Block 5 sheet 01 A-00-005 Rev. A received by the Local Planning Authority on 17th August 2018

Proposed floor plans Block 5 sheet 02 A-00-006 Rev. A received by the Local Planning Authority on 17th August 2018

Proposed elevations Block 5 A-01-005 Rev. A received by the Local Planning Authority on 17th  ...  view the full minutes text for item 37.

38.

Delegated Decisions pdf icon PDF 122 KB

To consider a schedule of applications determined under delegated powers during the month of August 2018.

Minutes:

Consideration was given to a schedule of applications determined under delegated powers during the month of August 2018.

 

RESOLVED that the schedule be noted.

39.

Date of next meeting

Tuesday, 6th November 2018 at 6.00 pm.

Minutes:

Tuesday, 6th November 2018 at 6.00 pm.

40.

Jessop Court, Quedgeley - 17/01364/FUL pdf icon PDF 840 KB

Application for determination:-

 

Construction of a distribution warehouse with associated offices, parking, sustainable drainage and new access off Marconi Drive  at Jessop Court, Quedgeley.

Minutes:

The Principal Planning Officer presented the report which detailed an application for the construction of a distribution warehouse with associated offices, parking, sustainable drainage and new access off Marconi Drive at Jessop Court, Quedgeley.

 

She drew Members’ attention to the late material which contained the views of the Highway Authority and an amended recommendation by the Planning technical Manager together with revised conditions.

 

Mr Russell Price, on behalf of the applicant, addressed the Committee in support of the application.

 

The Chair moved and the Vice-Chair seconded that planning permission be granted in accordance with the recommendation of the Planning technical Officer contained in the late material.

 

RESOLVED that planning permission be granted subject to the following conditions:-

Condition 1

The development hereby permitted shall be begun before the expiration of three years from the date of this permission.

 

Reason

Required to be imposed by Section 91 of the Town and Country Planning Act 1990 as amended by Section 51 of the Planning and Compulsory Purchase Act 2004.

 

Condition 2

The development hereby permitted shall be carried out in accordance with the application form, and drawing numbers 5067-01, 03c, 04b, 05b, 06b, 07b, 09b and 12 except where these may be modified by any other conditions attached to this permission.

 

Reason

To ensure that the development is carried out in accordance with the approved plans.

 

Condition 3

Notwithstanding the submitted drawings, no development above DPC level shall take place until there has been submitted to and approved in writing by the Local Planning Authority a plan indicating the positions, design, materials and type of all boundary treatments to be erected.  The boundary treatment shall be completed in accordance with a timetable to be agreed in writing with the Local Planning Authority.  Development shall be carried out in accordance with the approved details and thereafter maintained in a suitable condition.

 

Reason

In the interests of visual amenity of the area in accordance with Policy SD4 of the adopted Joint Core Strategy (2017).

 

Condition 4

No development shall take place, including any works of demolition, until a Construction Method Statement has been submitted to, and approved in writing by, the Local Planning Authority. The approved Statement shall be adhered to throughout the construction period. The Statement shall:

i.              specify the type and number of vehicles;

ii.            provide for the parking of vehicles of site operatives and visitors;

iii.           provide for the loading and unloading of plant and materials;

iv.           provide for the storage of plant and materials used in constructing the development;

v.            provide for wheel washing facilities;

vi.           specify the intended hours of construction operations (including demolition and preparatory groundworks)

vii.          specify measures to control the emission of dust and dirt during construction.

 

Reason

To ensure that appropriate measures are in place prior to the commencement of development to reduce the potential impact on the public highway and accommodate the efficient delivery of goods and supplies in accordance with the National Planning Policy Framework and to safeguard residential amenity and prevent  ...  view the full minutes text for item 40.