The Fleece Inn- Gloucester Report

Meeting: 06/12/2017 - Cabinet (Item 70)

70 Regeneration of the Former Fleece Inn Site pdf icon PDF 159 KB

To consider the report of the Cabinet Member for Regeneration and Economy  seeking approval to take the Fleece site to the open market to secure a partner to deliver a regeneration scheme that safeguards its future.

 

Additional documents:

Decision:

RESOLVED that:

           

1.            Officers be instructed  to prepare a development brief for the Fleece site that  sets the parameters for the development scheme, in consultation with the Cabinet Member for Regeneration & Economy

 

2.            A soft market testing and appropriate tender exercise, based on the brief, be undertaken by the Managing Director in consultation with the Cabinet Member for Regeneration & Economy, to test the commercial appetite for the various options for the site and to secure an investor/developer partner

 

3.            A further report be brought back to Cabinet in March 2018, detailing the basis of the proposals received and identifying a preferred partner

 

Minutes:

Cabinet considered the report of the Cabinet Member for Regeneration and Economy that sought approval to take the Fleece site to the open market to secure a partner to deliver a regeneration scheme that safeguards its future.

 

The Cabinet Member for Housing and Planning commented on the complex nature of the site and welcomed the approach being taken to generate a greater range of options to explore from which the best can be adopted.

  

 

RESOLVED that:

           

1.            Officers be instructed  to prepare a development brief for the Fleece site that  sets the parameters for the development scheme, in consultation with the Cabinet Member for Regeneration & Economy

 

2.            A soft market testing and appropriate tender exercise, based on the brief, be undertaken by the Managing Director in consultation with the Cabinet Member for Regeneration & Economy, to test the commercial appetite for the various options for the site and to secure an investor/developer partner

 

3.            A further report be brought back to Cabinet in March 2018, detailing the basis of the proposals received and identifying a preferred partner