To grant £100,000 from existing
Temporary Accommodation budget to Gloucester City Homes for
temporary accommodation for families in Southgate Street.
Decision Maker: Head of Communities
Decision published: 14/01/2021
Effective from: 07/01/2021
Decision:
To grant £100,000 from existing Temporary Accommodation budget to Gloucester City Homes for temporary accommodation for families in Southgate Street.
Wards affected: Westgate;
Lead officer: Ruth Saunders
A decision has been taken by the Leader, to
approve the following written resolution, as the shareholder
representative for Gloucestershire Airport Limited (the
Company):
• To approve the appointment of Karen Taylor to the role of
Managing Director and as a statutory Director of Gloucestershire
Airport Limited (GAL)
Decision Maker: Leader of the Council
Decision published: 07/01/2021
Effective from: 04/01/2021
Decision:
A decision has been taken by the Leader, to approve the following written resolution, as the shareholder representative for Gloucestershire Airport Limited (the Company):
· To approve the appointment of Karen Taylor to the role of Managing Director and as a statutory Director of Gloucestershire Airport Limited (GAL)
Wards affected: (All Wards);
To vary the agreement for the provision of
homeless outreach services dated 3rd August 2017 to extend the term
until 31st December 2021, and subsequently as necessary to reflect
any additional funding that may be granted as described in
“Reasons for decision” below.
Decision Maker: Head of Communities
Decision published: 04/01/2021
Effective from: 04/01/2021
Decision:
To vary the agreement for the provision of homeless outreach services dated 3rd August 2017 to extend the term until 31st December 2021, and subsequently as necessary to reflect any additional funding that may be granted as described in “Reasons for decision” below.
Wards affected: (All Wards);
To enter in to a Funding Agreement with GFirst
LEP in the sum of £4.3m for the purpose of redeveloping
Gloucester Railway Station in accordance with the Cabinet Report
considered on 6th February 2019.
Decision Maker: Leader of the Council
Decision published: 04/01/2021
Effective from: 16/12/2020
Decision:
To enter into a Funding Agreement with GFirst LEP in the sum of £4.3m for the purpose of redeveloping Gloucester Railway Station in accordance with the Cabinet Report considered on 6th February 2019. |
Wards affected: Westgate;
Lead officer: Ian Edwards
Agree to Gloucester City Council awarding a
short-term contract to P3 using a ‘direct award’. This
will be a pilot project with a partial mobilisation for 3 months
and the full pilot operating for a further 6 months.
Decision Maker: Cabinet Member for Communities and Neighbourhoods
Decision published: 31/12/2020
Effective from: 09/01/2021
Decision:
Agree to Gloucester City Council awarding a short-term contract to P3 using a ‘direct award’. This will be a pilot project with a partial mobilisation for 3 months and the full pilot operating for a further 6 months.
Wards affected: (All Wards);
Decision Maker: Head of Place
Decision published: 31/12/2020
Effective from: 31/12/2020
Decision:
To grant £33,000 from S106 commuted sums to Gloucester City Homes for temporary accommodation in Southgate Street.
Wards affected: (All Wards);